Smart Sun Energy

“MNRE approved Vendor for TANGEDCO”

FAQ

Frequently Asked Questions on Simplified procedure for installation of rooftop solar (RTS) projects

1. Basic information of grid connected rooftop solar PV system and MNRE scheme?
2. What is simplified procedure for installation of rooftop solar PV system?

In addition to the existing procedure of tendering/empanelment by the state electricity distribution companies (DISCOMs), MNRE has introduced a simplified procedure through which the beneficiaries can install the rooftop solar project either by themselves or through any vendor of their choice. Under this procedure, it will not be mandatory for the beneficiary to install the project only through the vendors empanelled by the DISCOMs. The beneficiary will have to apply online at the National Portal for installing the RTS system and the subsidy/CFA will be transferred to the bank account of the beneficiary directly after successful installation of RTS project.

3. What is the National Portal (NP)?

MNRE has developed a ‘National Portal (NP)’ for the registration of applications under the simplified procedure. The whole process from submission of application to the release of subsidy/CFA would be implemented in online mode through this portal.

4. How can I register on National Portal (NP)?

For registration at NP, the applicant will need electricity bill, an active 10-digit Mobile number and an active E-mail ID. The consumer will also be required to download SANDES App on his mobile. First, the applicant has to visit the registration page of national portal and select the state and the concerned DISCOM. Then the applicant has to enter consumer account no. mentioned in the electricity bill, mobile number and mail id. After entering these details, an OTP will be sent through SANDES App for mobile number verification. On successful verification of the mobile number, an account activation link will be received on the mail-id provided. The activation link will also include the details of the simplified procedure. After clicking on the activation link received in the email, the account would be activated and the beneficiary will be redirected to NP for submission of application.

5. Is there any application fee for applying on NP?

No, there is no application fee for submission for application on national portal. However, there may be fees for net-metering which may be charged by the respective DISCOMs.

6. Can I apply for net-metering through NP?

Yes. An applicant can apply for net-metering and inspection through the national portal. The application process of NP has been uploaded on the portal.

7. What bank details are required for the release of subsidy through NP?

After receipt of the online commissioning/completion report from DISCOM, the applicant will have to enter following details for claiming subsidy/CFA:

  • Name of the beneficiary
  • Account number
  • Bank Name
  • IFS Code
  • Copy of cancelled cheque to be
  • uploaded on the portal
8. How can I raise a complaint/ grievance, in case of non-receipt of subsidy amount in a given time?

You need to raise a complaint under the grievance section on NP.

9. What would be the cost of the system charged by the vendor under simplified procedure?

Under simplified procedure, the cost of the system would be mutually decided by the consumer and the vendor. However, the consumer can get idea of the prevailing market rates of the RTS system through benchmark cost issued by MNRE and the cost discovered in the different states.

10. How can I ensure quality of the system installed by the vendor?

MNRE has issued technical standard and specification for various components of RTS plant. The consumer shall sign an agreement with the vendor that the installation and commissioning of the RTS system would be in accordance with the technical standards and specifications issued by MNRE. MNRE has prepared a model agreement and the same can be adopted by the consumer.